The Right Order for Trades in a NZ Renovation

One of the most common (and expensive) renovation mistakes is getting trades in the wrong order. The painter shows up before the plasterer is done. The tiler starts before the plumber has set the drain position. Suddenly you're paying people to stand around, or worse, ripping out finished work.

Here's the sequence that experienced builders and project managers follow for a typical NZ residential renovation.

Phase 1: Planning (Before Any Work Starts)

  1. Designer or architect — plans, specs, and consent drawings
  2. Building consent — submit to council and wait (budget 4–8 weeks)
  3. Builder / project manager — lock in your lead contractor and timeline
  4. Order long-lead materials — kitchen cabinetry, imported tiles, specialty fixtures (some take 8–12 weeks)

Phase 2: Strip-Out and Structural

  1. Demolition — remove existing fittings, walls, flooring. Asbestos testing first if the house is pre-2000.
  2. Structural work — new openings, steel beams, framing changes. Council inspection at framing stage.
  3. Roofing (if applicable) — get the building weather-tight before interior work begins.

Phase 3: Rough-In (First Fix)

This is where pipes, wires, and ducts go into walls and floors before they get closed up.

  1. Plumber (rough-in) — water pipes, waste pipes, shower drains positioned
  2. Electrician (rough-in) — cables, switch boxes, lighting positions
  3. HVAC / heat pump — ducting if applicable
  4. Insulation — walls and ceiling before lining goes on

Council pre-line inspection happens here — before walls get closed up.

Phase 4: Lining and Wet Areas

  1. Plasterboard / GIB lining — walls and ceilings
  2. Plastering and stopping — tape, fill, sand (usually 2–3 coats)
  3. Waterproofing — bathroom and shower membranes (must be done before tiling)
  4. Tiler — bathroom floors, walls, kitchen splashback

Phase 5: Second Fix and Finishing

  1. Plumber (second fix) — install taps, toilet, shower head, vanity connections
  2. Electrician (second fix) — install light fittings, switches, power points, rangehood
  3. Kitchen install — cabinetry, benchtop, sink, appliances
  4. Joiner / carpenter — doors, skirting boards, scotia, shelving, wardrobe fitouts
  5. Painter — walls, ceilings, doors, trims (always after plastering and before final floor)
  6. Flooring — carpet, vinyl, or timber (last to avoid damage from other trades)

Phase 6: Final

  1. Final clean — construction clean before handover
  2. Final inspections — building inspector, plumbing sign-off, electrical Certificate of Compliance
  3. Snag list / defects walk-through — walk through with the builder and note anything that needs fixing
  4. Code Compliance Certificate (CCC) — applied for after all inspections pass

Common Mistakes That Cost Money

Do You Need a Project Manager?

For a small renovation (one bathroom, kitchen refresh), your builder can usually coordinate the trades. For anything involving multiple rooms, structural changes, or a budget over $80,000, a dedicated project manager can save you money by keeping trades on schedule and catching problems early. Budget 10–15% of the project cost for PM fees.